Welsh Requirements for Silage & Slurry Stores

Following changes to the regulations in April 2021,  farmers in Wales have to notify Natural Resources Wales (NRW) at least 14 days prior to any construction works on any new stores, or for substantial improvements to existing stores. Those that don’t notify NRW, risk an unlimited fine and even prosecution. 

The requirement forms part of SMR 1 – Water Protection. 

Natural Resources Wales says the ideal time to notify them is at the design stage. The notification is required for the following construction proposals: 

  • New silage or slurry stores 
  • Substantially reconstructed or enlarged stores 
  • Any facilities that are being repurposed for storing silage or slurry 
  • All of the above including field and non-baled, bagged silage sites 

Farmers making substantial changes to existing stores must make sure they meet current standards which can be found here: Natural Resources Wales / Silage and slurry storage 

Scroll to Top
Marketing Permissions

CXCS will use the information you provide on this form for the sole purpose of communicating helpful reminders, industry information and the latest CXCS news.

You can change your mind at any time by clicking the unsubscribe link in the footer of any email you receive from us, or by contacting us at dataprotection@cxcs.co.uk. We will treat your information with respect. For more information about our privacy practices please visit our website. By clicking below, you agree that we may process your information in accordance with these terms.